Post by Griffin » Sun Sep 08, 2019 5:58 am

Could you please add a filter option that you can hide all the tasks that still have unfinished dependencies?

I use the tree view to structure projects and the list view to see only the 'next actions' at a time. For tasks that have to be processed one after the other, I am currently using a workaround by defining the predecessor as a subtask and hiding the main tasks in the list view.

Unfortunately, this does not work if multiple tasks can be processed in any order as soon as a shared requirement has been met.

Image

Image

In this case the list view should only show the task "Clear all furniture out of the room", since both other tasks (paint the ceiling, remove the old wallpaper) can only be processed after this task is completed.

Maybe there is already a way to handle this in ToDoList, which I have not found yet. In this case, I would be very grateful for a hint. Otherwise I would be a happy camper if you could add a new filter option "Hide tasks with unfinished dependencies" (for the list view):

Image

Thanks in advance for your help!