There is a built in calculation attribute showing number of days remaining until 'Due Date' which I use heavily. But I also want to know how may days have elapsed since the 'Start Date' of a task. Please correct me if I am wrong, but I don't think there is currently a way to show this.
Would be great if there was way to use a 'Today' token in a custom calculated attribute to be able to create an attribute to show this.
Thanks for considering it.
A possible way to implement this...
Custom calculated attribute - current date token Topic is solved
Moderator: abstr
Re: Custom calculated attribute - current date token
Good idea but non-trivial :)
Re: Custom calculated attribute - current date token
I hate when that happens!
Re: Custom calculated attribute - current date token
Added to 9.0.A1
Re: Custom calculated attribute - current date token
Thank you!
Mr. Non-trivial has met his match in Dan!
Mr. Non-trivial has met his match in Dan!